Chapelcross Technology Campus
Application for planning permission in principle for up to 162,000m² of data centre floorspace in eight buildings on about 57 hectares north of the former Chapelcross nuclear power station near Annan. Each building is described as 120MW, and the developer calls it a 1GW campus. Dumfries and Galloway Council validated the application on 28 September 2026, with comments open until 19 November 2026.
- Operator
- CX Tech Ltd
- Location
- Annan, Dumfries and Galloway
- Status
- Planned
- Capacity
- 960 MW
- Planning reference
- 26/1649/PIP
- Last checked
- 2 Nov 2026
The pin shows the town, not the exact site.
Sources
Spotted something out of date? Send a correction.