Larbert Data Centre Campus
Full planning application for an AI data centre with 300MW of demand utility capacity on 18.92 hectares north-east of Glenbervie Nursery, Stirling Road, Larbert. It proposes two data centre buildings about 25 metres high. Falkirk Council held a pre-determination hearing on 16 September 2026, and the application was still awaiting a decision when last checked.
- Operator
- Apatura
- Location
- Larbert, Falkirk
- Status
- Planned
- Capacity
- 300 MW
- Planning reference
- P/26/0237/FUL
- Last checked
- 2 Nov 2026